The following EE measures were implemented:
- Joinery was replaced
- Thermal insulation of facade was installed
- Sheet-metal work was performed
- Thermal insulation was installed on the ceiling of the last floor of the building
- Luminaries were installed in all rooms where the replacement of suspended ceilings was performed.
- All related construction and specialists trades during the works were performed on the facade, as follows: replacement of gutters, sheet-metal work, tiling works, painting works etc.
- New boiler room was built and new heating boilers with necessary additional equipment were installed
|