Special hospital Jovan Bulajic - Brezovik
PROJECT NAME: MEEP
OBJECT TYPE: Hospital
MUNICIPALITY: Nikšić
YEAR OF REALIZATION OF WORKS:  2013
SURFACE OF THE OBJECT (m2): 4654
INVESTMENT (€): 487585.95
SPECIFIC INVESTMENT (€/m2): 104.77
ENERGY SAVINGS (kWh):  0
APPLIED ENERGY EFFICIENCY MEASURES:

The following EE measures were implemented:

  • Joinery was replaced  
  • Thermal insulation of facade was installed  
  • Thermal insulation was installed on the ceiling of last floors of the building
  • All accompanying construction and specialists trades were performed during the works on the facade, as follows: replacement of gutters, sheet-metal work, painting works etc.
  • New circulation pumps with variable speed drives were installed
  • Installation of thermostatic radiator valves on all radiators in all pavilions of the hospital etc.
  • Compensation of reactive energy was performed
PHOTOS: